One
(1) 50 Hz 20-30 MW multi-fuel fired complete power plant
Start-up:
1989 Shut-down: 2003 Conditions: excellent, still
installed
The
plant is composed by two steam generators (I and II) feeding the
same steam turbine generator
set
(ST1063G). Steam production @ 73 bar g, 495 °C, 90 tons/h (I) +
50 tons/h (II).
Steam
generator I (35.000 running hours,"As New") fired with
coal, natural gas, woodchip, sugarcane bagasse, rice husk, etc..
Steam generator II (50.000 running hours, in excellent conditions)
fired with natural gas, fuel oil.
Sale
of single equipment is also possible (i.e. 90t/h multifuel fired
steam boiler, 50t/h natural gas/oil fired steam boiler, stg-set,etc..).
Original technical documentation and pictures are avalaible.
Complete
OEM package with all auxiliaries (coal stocking, handling and
feeding system included).
|
| PP181
|
One
(1) 50 Hz 38 MW_el & 67 MW_th dual fuel (natural gas / diesel
oil) fired complete CHP plant
Start-up:
1975 Stand-by mode: 1975-1996 Continuos
mode: 1996-2005 Running
hours: 44.258 (up to 07/04)
Repowering:
1997 Main
revision: 2003 Running hours after
revision: 3.000 (up to 10/04)
Conditions:
excellent, still installed The plant is
composed by one (1) 50Hz, 15kV, 38 MW_el Fiat/Westinghouse dual
fuel (natural gas / diesel oil) gtg package and one (1) HRSG
producing superheated water @ 1.200 tons/h, 120 °C, 16 bar.
Original technical documentation and pictures are avalaible.
Complete
cogeneration power plant with all auxiliaries (electrical
equipment, main step-up transformer, heat recovery generator,
stack, Cummins diesel launching engine, 400kW emergency diesel
genset, ABB exciter-new in 2001, de-frost system, interconnecting
piping, etc..)
|
| PP184
|
One
(1) 50 Hz 500 MW dual fuel (natural gas / diesel oil) fired
complete power plant
4
x 125 MW @ ISO Cond. Fiat/Westinghouse gtg packages Manufactured
in 1994 Designed for natural gas and diesel oil firing
Unit
1 Unit 2 Unit 3 Unit 4 Commissioning: 1996 1996 1995
1995 Equivalent operating hours (as of Oct. 2004): 20.000,
28.500, 39.400, 46.200 Conditions: excellent
Equipped
with by-pass stacks for simple cycle operation and configured
for feeding water pre-heating ABB Electrical generators @
140 MVA, 125 MW, 15 kV, cos phi 0.9, 3000 rpm Cooling
system: hydrogen
Exciters:
ABB Static. Main Transformer: ABB, 15/400 kV. Each unit is
located in a separate enclosure and is equipped with its own
inlet filtration system, anti-icing system and water injection
for NOx abatement
LV,
MV panels, all electrical & auxiliary systems are included
in the scope of supply.
|
|
|